Construction of sewage tunnel: "A Malata — Priorño" (Ferrol, Spain)
Oct 05, 2006
The project is located in Galicia, in the Northwest of Spain. It is included in the Sewage disposal scheme from Ferrol. Its total investment is about 170 million euros. The Ministry of Environment, by means of the Confederación Hidrográfica del Norte, is the owner of the project. It is necessary the construction of a tunnel of 7.344 meter long and with 3.7 meters of excavation diameter. The tunnel is being executed at the present time, using an open face T.B.M. Robbins 1215-265. This text provides information related to geological and geotechnical characteristics, modifications of the project and complexities of the tunnel execution.
The project consists of the construction of a tunnel of 7.344 meters long, with an excavation diameter of 3,70 meters and an inside diameter of 3 meters long, with a slope of 1,86/1000 which will carry waste waters from the Pumping Station in La Malata towards the water treatment plant in the Prioriño Cape.
CROSS AND RISING MAIN OF LA MALATA: (18,645 million €). This action is made up of:
- Cross of the La Malata Bay
- Pumping Station
- Rising main to connect with the Sewage Tunnel.
Hydraulic tunnel of 7.344 meters long and 3 meters of diameter that allows communication between the Pumping Station and the Prioriño Cape water treatment plant.
Water treatment plant of 6 hectares, which will make possible to treat an average flow of 1.150 l/s. with a system of treatment of active muds of high charge.
It is made up of:
- Disinfected UV rays in Sewage Tunnel head.
- Underwater tap with over 1.000 meters long.
Figure No 1 shows a scheme of the four mentioned projects.
The area of the project is located in the Galicia "Tras os Montes" area, originated from the Centro-Iberica Paleo-geografic unit, which extends itself from the Precambrian to the Devonian Age. It is a late intrusion of cylindrical shape of the Ordenes series.
The granodiorite is the present rock all over the tunnel. Its grain is of a half-thick size.
In general, it can be considered like a rock of great hardness and with a high level of quality.
These materials have been affected by a poliphasic tectonic of hercinic age. The detected faults present two principal positions:NO-SE, with dip towards the Northeast, and NO-SE, with a very vertical dip.
- Geologic mapping based in a photo geologic study of the area and a geologic mapping of field.
- Electric logs: 15 electric logs were done with a total length of 6.370 meters.
- Probe holes execution: 10 probe holes were done with a total of 800,35 meters.
The average permeability of the mass is about 10-7 and 10-8 m/s. The ground water level is very superficial, about 10 meters deep.
The chart below shows a summary of the geotechnical characteristics of the rock that crosses the tunnel, according to previous test:
Type of rock | Peso Esp.(T/m3) | Cohesion (Kp/cm3) | Friction Angle. (°) | Mass Deforma tion Module (Kp/cm2) | Poisson Ratio |
---|---|---|---|---|---|
Granite | 2.4 | 40 | 43 | 120,000 | 0.25 |
Fractured Granite | 2.2 | 10 | 40 | 35,000 | 0.25 |
Very weathered granite | 2.2 | 1-2 | 36 | 600-2000 | 0,30 |
The faults to the tunnel level, their position and dip have been all deduced from the layout of the faults in surface, detected by photo geology, from the drilling surveys, from the observations in the area and from electric logs.
In the geologic plant, it has been considered to represent sandy areas detected in field, which will correspond to faults of certain importance.
The biggest fault observed is the one of Valle de Cariño, in which there are important sandy areas, with caolinitizacion and areas of oxides associated to water running.
The tunnel will cross this fault between P.K. 3+210 and 3+400.
The overburden in the tunnel varies from 20 to 220 meters; such as it is shown in the geologic profile in Figure 2.
Due to uncertainty, which represents the excavation of an area of fault using a Tunnel Boring Machine (T.B.M.) for rock, before the beginning of the excavation of the tunnel, different possibilities were analyzed for the construction of the tunnel in the area of the Cariño Fault.
As a result of the study, four alternatives were analyzed:
Execution of a vertical shaft of access of approximately 110 meters long and 3 meters of free diameter in the fault area, to build a pilot heading parallel to the axis of the tunnel from which would be carried out a previous consolidation treatment of the area, before the T.B.M. arrived.
This option wouldn't modify the term of execution of the tunnel, since it could be begun together with the excavation of the tunnel.
To build a gallery in by-pass for the treatment of consolidation of the fault area, from the Sewage Tunnel, leaving from the end of the back up, approximately to 170 meters of the front, once the cutter head of the tunnel reaches the beginning of the fault.
This option would represent the possibility of having to stop the excavation works with the T.B.M.; during the time the process of consolidation process of the fault area lasts.
Execution of a vertical shaft of approximately 110 meters long and 5 meters of free diameter in the adjacent area to the end of the fault, in order to proceed to excavate the plot of the Sewage Tunnel for conventional methods, with a section which allows the passage of the T.B.M. later on, to continue the excavation of the tunnel with mechanical means.
This option wouldn't modify either the term of execution of the tunnel, since it could be carried out at the same time that the excavation of the tunnel.
This alternative is similar to nº 2, but beginning the execution of the by-pass in the area immediately later to the Grippers of the T.B.M. and before the beginning of the back up.
This option would make possible the saving of the execution of the 170 gallery meters, even when, it would be also necessary to come to a standstill of the excavation of the T.M.B. and to take the necessary measures to guarantee the machine is not damaged with the excavation process with drill and blast method of the by-pass.
Parallel to the study of alternatives, an electric log was done in the area of the fault, whose results confirmed that the area was made up with materials with alteration grades of III, IV and V, but the tunnel length seriously affected by the fault it could be of the order of the 100 meters, half of that foreseen in the original project.
With these new elements, four probe holes with extraction and core drilling in the area of the fault were carried out to know the geology of the area with more accuracy.
As a result of these probe holes, it has been observed that the condition of the rock at the town level is much better than the one indicated in the electric log, and that the weathered area may be in the order of 30 meters.
According to the facts already exposed, it has been decided to reject the four studied alternatives and to do the excavation of the tunnel with the T.B.M., with a continuous pursuit of the geology of the excavation front.
It is possible to use a steel liner in the area, which has already been used in other tunnels carried out by the contracting firm with good results.
The design of the Sewage Tunnel’s type section required a study of alternatives in what different sections and constructive systems were managed, taking account aspects such as economic cost, execution term, environmental damages, functional aspects and constructive viability.
- No visit section: water would flow free through out the circular tunnel and executed by a T.B.M. with precast concrete segments.
- Service gallery: it was a visit section in which purification conductors would be hosted and water would flow free or by gravity through them.
Section | Type | Shape | Internal Diameter (m) | Excavation Method |
---|---|---|---|---|
1 | No visit | Circular | 3,00 | T.B.M. |
2 | Visit | Circular | 5,00 | T.B.M. |
3 | Visit | Circular | 6,00 | T.B.M. |
4 | Visit | Horseshoe | 5,00 | Conventional |
3 | Visit | Horseshoe | 6,00 | Conventional |
According to the suitable geologic conditions in the nearby whole of the tunnel layout, it was decided the placement of an invert precast concrete like against stable roof for the T.B.M. advance.
To stabilize the excavation until the lining is executed, three types of initial support have been projected based on rock bolts, steel ribs and wet mix shotcrete.
Rock type | % Use | Initial support |
---|---|---|
I | 65 | Occasional resin anchor bolts in rock wedges. L= 3 meters. |
IIa | 35 | 3 systematic resin anchor bolts of L=3 in roof, separated a meter in longitudinal sense. Shotcrete with steel fiber of 8 cm thick. |
IIb | TH-21 steel rib @ 1 meter. Shotcrete with steel fiber of 8 cm. thick. | |
III | 5 | HEB-120 Type steel rib @ 1 meter. Shotcrete with steel fiber of 12 cm. thick. |
- Implantation of the portals in favorable areas, both from the geotechnical point of view and from their placement in the cityplanning framework, especially in La Malata.
- Implantation of the tunnel in the most favorable geologic areas.
- Smaller possible length.
- Acceptable minimum radius to be able to carry out the excavation with a T.B.M.
According to the characteristics of the rocky mass to be crossed for the Sewage Tunnel, the project recommended the use of an open front T.B.M., without shield, with a power of 1.500 KW, a thrust around 900 ton and 28 cutters of 17’’, with a noun diameter of 3,70 meters.
In relation to the guidance, the machine should dispose of guidance and positioning system that make possible to know at any time its position and direction.
The main characteristics of the T.B.M. are:
Year of manufacture: 1.991
Model: 1215-265
Diameter of excavation: 3,70 meters.
Number of motors: 4
Power: 1.800 HP.
Speed cutterhead: 11.9 rpm.
Thrust: 875 ton.
Number of cutters: 26
Diameter of cutters: 19”
The main body of the machine has drilling hammers of rock bolts to both sides and a steel rib setting device.
The back up is a mobile structure that moves itself pushed by the own T.B.M. and disposes of all the necessary equipment to construct the tunnel.
- Operator’s cab of the machine.
- Cabin of operation and filling control of muck cars.
- Close circuit television and remote control operation placed in strategic parts of the T.B.M. with monitor in the operator’s cab.
- Grease pump and oil tanks for lubrication of the cutterhead.
- Refrigeration tanks for the lubrication oil.
- A warehouse.
- Transformers of 660 V. a 220 V. to feed auxiliary systems.
- Electric boards to feed the cutterhead.
- Generator for auxiliary systems of 20 KVA.
- Fans in stiff pipes of 400 mm. of diameter.
- Dust collector of the ventilation.
- Water pumps to feed refrigeration circuits.
- Coil of energy cable of 15.000 V with capacity for 300 meters.
- Compressor for rock bolts.
- Water tank for recirculation with 6 m3. of capacity.
- Dining room.
- Secondary conveyor belt to load the muck cars.
- Unloading system of invert precast ashlars by a tackle of 3 ton.
- Bag line cassette of 100 meters long.
- Gas detection system.
- Lighting system.
- Phone system among the operator’s cab, filling cab of the muck cars and the electromechanical factory located on the plain.
- Handrail.
- Operation system for the movement of muck cars by means of chains, without intervention of locomotives.
- System of traffic-lights to check the traffic of locomotives in the neighborhoods of the Californian switch rail.
This system allows determine automatically the exact position and the direction to follow, as well as the correction of the deviations with respect to the axis of the project, which has been previously introduced in the computer system.
The system has a motorized theodolite that makes continuous readings to two motor prisms, located in the main body of the T.B.M. and to a remote prism placed at the back that serves like direction element.
All this information is presented in a monitor in the operator’s cab, where the operator knows the exact position of the T.B.M. at any moment.
This system has been used in different projects worldwide in this kind of machines, as well as in roadheaders, EPB, microtunnels, etc.
This model of T.B.M. was designed by Robbins in 1991 for the project of Meeraker in Norway.
One of the main achievements obtained in the design of this machine is that for the first time in history, it was possible to excavate with a maintained loud of 32 ton by cutter.
In this project, it got an average advance of 253 meters a week, in a tunnel with 3,5 meters of diameter.
Later on, this machine was used to construct a tunnel of approximately 13 Km. in the Middle-East, Pipeline tunnel Medina Site 7 to Yanbu Oil Refinery (Saudi Arabia) which was ended at the end of 1997.
Usually, before the beginning of the excavation works of a tunnel, different alternatives are analyzed in relation to the use of equipment, what it is translated in modifications of technical character related to the constructive aspect of the work.
Among the main necessary modifications and changes to initiate the construction tunnel, we have:
The invert precast concrete of the project had 1,85 meters in crosssectional section to the tunnel and 3 meters in longitudinal sense to the advance.
With these dimensions, it was necessary the use of a tackle of great proportions in the area near to the back up of the T.B.M., to be able to transport the invert precast concrete, which are placed immediately after the Grippers area.
This situation was solved with the design of a new invert precast concrete of smaller dimensions.
The adopted invert precast concrete is of 1,613 meters of crosssectional section and it has 1,20 meters in the sense of the advance.
An advantage to emphasize of this change is that the new design of invert precast concrete has made possible a great versatility in the inside transport of the tunnel and has increased the placement yield of it.
This reduced invert precast concrete is similar to the normal one, but with a diminution in its inferior part that allows to place the complete ring of steel ribs.
This situation guarantees a better execution of the support in comparison with the original project, in which the steel rib was discontinuous, that is to say, it leaned laterally in the invert precast concreter.
The space between the invert precast concrete and the ground, once the steel rib is placed, is filled up with fluid concrete.
In Figure No 3, it can be appreciated a cross-sectional section of the new invert precast concrete that is being used in the works.
The T.B.M. has in the area immediately rear to the shield two lateral roof drills which make possible the placement of rock bolts. These roof drills have a limitation with respect to the placement of the rock bolts. It is only possible to perforate at roof level (between 10 and 2, according to the hour positions of a clock).
Another disadvantage it is the little existing room in the area, what took to the decision of placing bolt rocks of L= 1,30 meters instead the foreseen bolt rocks of 3 meters long.
Nevertheless, there are manual drillers in the work that allow to place rock bolts of the necessary length and in the required hour position, once the back-up of the machine has been passed.
The projected steel ribs were overlapped of the TH-21 and HEB-120 types, with the use of UPN-80 bracings, spaced one meter approximately.
Finally, it was decided to place TH-16.5 steel ribs, joined by means of the use of plates.
The separation of the steel rib was reduced to 0.75 meters because of two main reasons: the first one is that the steel rib is less strong, so the space between them has been reduced and the second one because of operative reasons of support to the gripper. It has been chosen to place steel ribs of four sectors.
This decision was taken with the purpose of placing a steel rib lighter, that would allow a better ease of construction and, at the same time, would reduce free jib between the placed steel rib and the T.B.M. back up.
Originally, it was foreseen the execution of two out lets galleries of 25 meters long, in the area of both main doors, in horseshoe tunnel, and excavation by means of drill and blast method. Finally, it was decided to do the outlet with the same T.B.M.
In order to do that, during the excavation of the plain, there were two rock walls left, covered with shotcrete, which were a support to the Grippers of the T.B.M. to initiate the excavation of the tunnel.
Previously to the beginning of the excavation of the tunnel, it was necessary to make a plain with an area of about 14.000 m2, zone from which would part the T.B.M. and where there would be the necessary installations to carry out the works.
Once the excavation of the tunnel is finished, this same area will be part of the water treatment plant. It was necessary the excavation of approximately 325.000 m3 of rock material, by means of the use of blasting.
The transport of the T.B.M. to the work was made by road, being a distance of 15 Km. of which, the four first were on motorway. The remaining kilometers run by narrow highways, with strong slopes, pronounced inclines and with close bends within a semi-urban space.
Additionally, there were two cranes in both ends of the convoy to be able to help the transport in the areas of high slopes, where the motor strength of the tractor heads was not enough to continue the way.
In total, the transport process to the work lasted approximately six hours. Figure 4 shows the arrival of the T.B.M. to the plain.
All the fittings of the tunnel are located in the excavated plane. Basically, they consist of:
For the electric feeding, there are in the work 5 generators from 810 KVA to 380 V. There are also 6 transformers from 380 V/15.000V. The electric control can be carried out from the T.B.M. operator’s cab or from the synchronization and joint cab placed in the plain.
Ventilation:
There are two fans in series with a power of 30 KW each one at the entrance of the tunnel. It is foreseen the placement of relief fans inside the tunnel once they are necessary.
The ventilation duct is a flexible pipe of 700 mm of diameter.
Air compressed: There is a portable compressor in the work that provides the required air.
Water supply:
It is required basically for the refrigeration of the T.B.M., for the cutterhead diffusers, for the rock bolts and for the cleaning of the back up. To this business, there are two tanks of 150 m3 each in the work.
It is pumped to the tunnel by means of groups of pressure through a metallic pipe of 3 inches of diameter.
There is a caudal meter for to register of the water pumped inside the tunnel.
Invert Precast Concrete storing:
Invert precast concrete are manufactured in a plant outside of the work; in the plain there is an area of about 500 m2 for their storage.
Excavation material storing: Room of approximately 4.000 m2 for the provisional storing of the muck material from the excavation of the tunnel.
Several storing:
Space reserved for the storing of rock bolts, steel ribs, wire mesh, Bernold type sheet, tracks, wind pipes, etc., with an approximate surface of 500 m2.
Gas oil tank: For the gas oil supply to the generators it has got a capacity of 20.000 litres.
Muck ditch:
Due to the fact that muck cars unload at the back, it was necessary the excavation of a ditch to empty out the muck coming from the tunnel. The material is gathered provisionally in the plain and later on, it is retired in trucks to the authorized dump.
Decanting basin:
In this basin, waters coming from the tunnel and from the muck ditch are collected for their decantation. It has an approximate surface of 70 m2 and a storage capacity of 120 m3.
Electro mechanic workshop:
It is where it takes place the maintenance and repair of T.B.M. pieces, system of cars, locomotives, mixer, etc.
Work offices:
Offices of the contractor, owner and inspection staff.
Dining room, changing rooms and toilets:
Rooms to be used by workers.
Parallel to the auxiliary installation in the plain, it was carried out the execution of the out let works in the plain of the Prioriño Cape.
The first stage of the outlet was the protection of the slope where the tunnel excavation would be initiated. There, works were to place injection bolts of 8 meters long and 25 mm of diameter in the outlet slope placed into squares of 2 m. H x 3 m. V and to place wire mesh made of corrugated round of 150 x150x6 mm.
It was also placed a shotcrete layer of 10 cm thick.
The second stage of the outlet was the execution of crown bars protection of bolts of 15 x 12 m long and 150 mm of diameter, with a distance among bolts axis of 30 cm.
All the bolts made were joined through execution of a shotcrete beam of 4.5 meters long and 600 x 600 mm of section.
By virtue of the work, it is being executed at the present moment, to the effects of the treatment of this chapter, we will show the advances and experiences obtained until the 28th February, dead top fixed by the organizers of the event for the reception of the works.
Excavation works of the tunnel began at the end of August 2004.
In a first stage, there was only a work shift, between 8 and 10 hours a day, which made possible the outlet of the T. B.M. and the entrance of the back up inside the tunnel.
At the end of November, once the back-up was inside the tunnel, a double shift was established of about 12 hours by shift, five days a week.
It is being considered the possibility to incorporate a third shift, with the purpose of working the 7 days of the week.
In Figure 6, it can be appreciated in the changes of slope, the impact produced by the advance of the excavation, as consequence of the implemented measures before mentioned.
All the transport of materials, mucks, invert precast concrete and personnel is done by trains.
There is the following equipment in the work at present:
- Two diesel locomotives of 15 Ton.
- 14 muck cars of 10 m3.
- 2 platforms for the transport of invert concrete precast.
- 3 personnel cars of approximately 12 seats.
- 1 mixer for shotcrete.
- 1 concrete gun.
The locomotive parks the two trains in the Californian switch rail and, by means of a change feed for the movement of the cars, one of it is taken to the back up for the removal muck of the excavation material.
The company in charge of the construction of the tunnel is NECSO Entrecanales y Cubiertas, company with a large experience in the construction of similar works.
To date of 28/02/2005, there are 1.032,222 meters excavated, which represents the 14,06 % of the total of the tunnel.
In spite of having in the work experienced personnel, there is always a process of adaptation to the excavation and support system and to the methodology, until it doesn’t get to fit the work equipments efficiently.
The obtained excavation records to date are shown in the following chart:
Advance (m) | Period | |
---|---|---|
Best shift | 15,033 | Nocturne Shift 17/02/05 |
Best day | 28,948 | 17/02/2005 |
Best Week | 108,644 | From 14 to 20/02/05 |
Best Month | 336,112 | February 2005 |
We can take out the following thing from the analysis of the cycle of work:
It is considered that many of the presented values are within the acceptable parameters according to analyzed experiences in the execution of similar projects with TBM.
A special mention to point up is the percentage of breakdowns and shutdowns. We consider that the percentage is high, however, it has reduced as the excavation advanced.
Among the main breakdowns and shutdowns, which have taken place, we can to point up:
- Conveyor belt of the TBM, as well as the conveyor belt of the back up. There were problems with the decentred of the belt in the rollers, with breakings of the belt and problems associated to the main roller, which has had to be replaced three times.
- Derailment of muck cars in the Californian switch rail.
- continue the excavation due to the impossibility of placing ashlars, on which the back-up of the machine is leaned.
- Cleaning of the buckets of the cutterhead.
- Failures in the operation of the PPS system.
- Electric failure in the motors of the cutterhead.
Project monitoring
The project regarding to monitoring, contemplates the installation of instruments and monitoring systems that guarantee to control the movements of the tunnel, as well as the surroundings rock, water pressures, support and lining reactions.
In general, the application of measures will help to know deformations, operating strengths and land decompressions. In relation to deformations, convergence measurements will be done in the tunnel.
With relationship to the forces and pressures, vibrating wire extensometers pairs will be installed in order to measure flexion efforts in the lining.
Additionally, vibrating wire piezometers and manometers will be placed to detect the existent pressure against the lining. On the other hand, horizontal vibrating wire piezometers will be placed to check hydrostatic pressures in the mountain.
To know the decompressions of the rock, rod extensometers will be installed, that will make possible to control the way the decompression area around the built tunnel progresses.
As a result of diverse meetings with the contracting firm, the Work Management and other specialists in the matter, it has been consider that the monitoring defined in the project was very intensive, for what it was decided to do an evaluation of it and to implant in the work different criteria.
- Placement of convergence measurements stations each 50 meters approximately, the convergence measurements pins, will be placed immediately behind the Grippers of the T.B.M. (about 15 meters of the excavation front), area where it is possible to make a measurement of the springline.
- Placement of rod extensometers pairs each 50 meters, immediately after the shield of the cutterhead, in the area where the roof drills are placed (about 6 meters of the excavation front).
- Placement of invert vibrating wire vertical piezometers, once it has passed the back up of the T.B.M., that is to say, to approximately 230 meters of the excavation face.
Nevertheless, we consider that a good monitoring plan correctly developed allows know with more accuracy the behaviors of the tunnel and so, to be able to confront preventively whatever anomaly is presented.
In the Sewage Tunnel, the monitoring process has been delayed for different reasons and so far, seven convergence measurements stations have been placed, where the accumulated convergence measures are in the order of a tenth of millimeter.
A vertical piezometer has been placed in the P.K. 0+502,00. Preparations works have being done to carry out the first station of a rod extensometers pair.
The Work Managing is in charge of the ConfederacIón Hidrográfica del Norte, whose team is formed by the Work Director and a Technician.
The control and surveillance is carried out by the team of the Technical Attendance to the Work Managing in charge of the Eptisa Company.
Carried out works to date, are the normal ones in this kind of labour, such as: surveillance in the construction of the tunnel, the topographical control, measurements, the supervision of the project, as well as the surveillance of the monitoring process and the geology of the excavated tunnel.
It is also carried out a pursuit to the quality plan and the production process of the invert precast concrete in the manufacture plant.
The project of construction of the Sewage Tunnel is within a set of works approved by a Law of the State and according to Evaluation of Environmental Impact Royal Legislative Decree 1302/1986, it is not necessary to do an Evaluation of Environmental Impact of the project.
The Costa Artabra is within the Galician Community, a Natural Space in regime of general protection declared by Order.
With this Order, the areas proposed by the Galician Community to include in the European Network Natura 2000 are provisionally declared as Natural Spaces in regime of general protection.
- Identification of damages or environmental effects.
- Description of damages and evaluation/valuation of the repercussions.
- Implementation of correct and protective measures against noise, dust, gas or scents discharges, against the erosion, about water, vegetation, fauna, landscape and archaeological heritage, which should be carried out during the execution of the work.
Another important aspect to emphasize is the accomplishment of a technical study about water filtrations and the hydro geologic impact produced by the construction of the tunnel. This study is being done by means of a contract for technological support activities signed with the Santiago the Compostela University.
- Hidroclimatical study of the area: it consists of the update and data processing from the climatic station owned by CIS Ferrol.
- Analysis of the obtained results of the hydro geologic works of the project.
- Hidrogeologic and physicochemical data collected in the sampling points: data such as: volume, electrical conductivity, water temperature and pH.
- Analysis of the pursuit of the monitoring process of the tunnel and measurement of infiltration volumes.
Andreani C, Luis. Sistemas auxiliares utilizados en tuneladoras. Curso de “Pasos necesarios en la selección de tuneladoras”. IIR. Madrid. Noviembre 2004.
Dollingrer, Gerald et al. An Update on the performance of large diameter (483 mm) cutters and high performance TBMs. 1993 RETC Proceedings. Pp.781-792.
Hansen Arnulf M. The history of TBM Tunnelling in Norway.
McLearie D. D., Foreman W., Hansmire W.H., Tong E.K.H., (1991) Hong Kong Strategic Sewage Disposal Scheme Stage I. Deep Tunnels. 2001 RETC Proceedings. Pp.487-498.
Molinero H. Jorge, Raposo G. Juan R., Docampo C. Eva. 3º Informe de Progreso. Estudio de las infiltraciones de agua y del impacto hidrogeológico producido por la construcción del túnel para el Emisario Terrestre “A Malata – Cabo Prioriño”. Febrero de 2005.
Propuesta definitiva de anteproyecto modificado para el tratamiento del terreno en la zona de falla del entorno del P.K. 3+350. Emisario Terrestre “ A Malata – E.D.A.R. de Cabo Prioriño”. Ferrol. S.P.I.C y A.G.I. Octubre del 2004. Proyecto Constructivo del Emisario Terrestre: A Malata – EDAR de Cabo Prioriño (Depuración y vertido de Ferrol). Saitec Ingenieros. Septiembre del 2002.
Steinar Johannessen & Odd G. Askilsrud. Meraaker Hydro – Tunnelling the “Norwegian Way”. 1993 RETC Proceedings. Pp 415-429.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Tunnelbuilder Ltd.
England (UK)
Phone:
+44 1892 545750