Double triumph for HDD in the Middle East
Aug 26, 2010
Carsten Fischbach of DrillTec GUT reports on two difficult undersea HDD projects in the Middle East, both of which have set a record in their own way.
With the successful installation of a 1,500 m long, 760 mm pipeline landfall at Abu Ali island in 2008, oil giant Saudi Aramco achieved the first application of HDD technology for a pipeline shore approach in Saudi Arabia, as well as the first project of its kind in the company's history.
In preference to conventional dredging and trenching, the world's number one oil producer decided to further explore this advanced alternative method and use it for the trenchless installation of a 400 mm oil pipeline over a distance of 2,100 m across a shallow water zone and on to the shore. It would carry crude oil from the Qatif offshore field on to land. German HDD specialist DrillTec GUT, which also carried out the first crossing in 2008, was entrusted with the work.
Horizontal directional drilling (HDD) was chosen as the preferred method of installation. This arose out of concern for protecting marine life on the near shore, but also to safeguard the pipeline against wash-out and exposure to wear and mechanical stresses in the shore and breakwater zone.
The tight schedule and narrow weather window for operating a pipe-laying barge in the relatively shallow waters around Qatif could have endangered the viability of the project. For these reasons, DrillTec and Global Industries, the main contractor and a US-based offshore specialist, decided to pre-fabricate the HDD pipeline section and lay the string on the seabed about two weeks ahead of the planned installation date. This would make the installation independent of the availability of a pipe-laying barge and was a factor, which enabled the construction team to complete the crossing within the scheduled period, despite temporary bad weather.
Although the mainly calcaronite and limestone geology conditions caused only minor difficulties during drilling, the overall length of the bore required regular cleaning and reconditioning of the borehole, especially during the pilot stage. In addition, it was decided to install about 250 m of conductor casing within the onshore entry section to avoid frac-outs of drilling fluid through the relatively soft topsoil layers. The casing also provided support to the drill string as required to generate sufficient thrust in order to penetrate the seabed with the planned angle and accuracy.
To achieve this goal, DrillTec used subsea steering coils at the offshore target area and an intermediate location along the drill path, which enabled deployment of a magnetic-based wireline-steering system. This allowed verification of the drill-head position at those stages and the implementation of necessary corrections to the bore trajectory, as required. Divers were used to install those cable coils ahead of the HDD operation and accurately survey their position after having anchored them to the seafloor using concrete blocks. During drilling, the coils were temporarily energised using a small support boat carrying a suitable power source.
Throughout the operation, fresh drilling mud had to be continuously injected into the borehole to counteract mud losses in the hole; this task was performed by using efficient mud-cleaning systems that enabled reconditioning of the fluid returning to the surface, thereby reducing the amount of bentonite required and the waste mud that had to be disposed.
Finally, and after only 27 days of non-stop operation round the clock, the almost 2.2 km-long section of 400 mm steel pipeline was connected to the drill string by divers after it had been dewatered using caliper pigs powered by compressed air. Dewatering was necessary as, after it had been laid on the seabed, the pipe string was filled with water to prevent it moving as a result of subsea currents. To further stabilise the pipe's position, gravity anchor blocks were placed on the seafloor at both ends of the string.
Abu Dhabi's water and electricity supplier, Transco, required two 400 kVA high-voltage power circuits to be laid between Abu Dhabi's industrial port and the newly developed island of Saadiyat. This was to ensure the strategically important island would have electricity in time for the planned opening of new residential and commercial facilities there.
DrillTec GUT, in association with its long-term joint-venture partner and local, main contractor, NSCC International, had previously installed several 1,220 mm-long water pipelines using HDD for Transco as key elements of earlier major development projects. In early 2009, NSCC-DrillTec in co-operation with UAE-based power specialist Al Barrak, were awarded the challenging Transco contract.
Due to technical restrictions on the production of the 400 kVA cable sections and the necessity to have the underwater crossing installed in one piece without any intermediate joints, both entry and exit points of the HDD borehole had to be located near the shoreline on either side in order to overcome the channel width of about 800 m. This resulted in relatively steep bore angles to allow sufficient coverage above the borehole to safely cross beneath the shoring structures on both banks of the channel.
The restricted space conditions on either side of the crossing also meant that the pilot hole had to be drilled with a very high accuracy to hit the target. This was a challenge in itself since the crossing was situated between a parallel, eight-lane road bridge under construction on one side and two 1,200 mm steel pipelines previously installed on the other side.
Another task for the drilling team was the temporary high loss of drilling fluid downhole and the non-availability of a mud-return option for the first line; this was solved by using two HT400 high-pressure mud pumps, enabling the injection of drilling fluid into the borehole from either end of the drill string. This reduced the amount of mud generated and eliminated the need to transport drilling fluid between the sites.
Before bundling, the pipes were pressure-tested, and then joined to a specially-designed and fabricated pulling head; the string required backhoes and other equipment along its almost 1,000 m length to provide lifting support and ensure the required alignment was maintained.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
DrillTec GUT GmbH
94469 Deggendorf
Phone:
+49(0)991 37212-400
Fax:
+49(0)991 37212-409