Microtunneling to Exacting Standards in Holland
Jul 07, 2005
Not only were ground conditions difficult and the water table high, but also tunneling under an excavated canal with banks higher than the surrounding land required exceptional safety measures.
The WRK I and II pipelines between Utrecht and Abcoude run parallel with the A2 Freeway. During the next few years, Rijkswaterstaat (Directorate-General for Public Works and Water Management) is going to expand the A2 Freeway between Amsterdam and Utrecht from three to four lanes. For this reason, the pipeline to the east of the freeway must be moved some 60 m eastward over a distance of about 5 km.
Amsterdam Water carried out the preparatory survey work itself and had been able to decide the course the pipes needed to follow. After a pre-selection process, a building consortium, Visser & Smit Hanab, Papendrecht, Netherlands/Dura Vermeer Infra, Hoofddorp, Netherlands, was chosen as the most suitable partners. Good cooperation between Amsterdam Water and the chosen partners meant that a quick match between the owner's theoretical approach and the contractor's practical approach was possible and this saved time to produced a good, final, detailed plan.
In the soft peat soil, the boring machines could not be offset against the sheet piling as they would normally. The clay/water mixture does not exert much counter-pressure, so the piling would simply be pushed away unless additional measures were taken. For this reason, large profiles were filled in the middle of the concrete floor with frames behind it to offset the drilling frame and transfer the thrust to the surroundings through the concrete floor.
After the new pipeline had been laid and connected to the existing one, the section to be replaced was removed. This meant removing around 1,500 concrete pipe sections. Because the system could not be shut down completely and water transfer had to be maintained throughout, the pipelines were connected one at a time.
The new part of the freeway is being built on an enormous sand bank whose weight compresses the peat soil layer. Everything else under the freeway can also be compressed and moved, including a pipeline. So, after examining the various options, Amsterdam Water chose to relocate the new pipeline as deep as economically possible. The traditional method of construction by excavating a trench was also discounted because it would have been very expensive and complex since the peat extends from the surface to a depth of 6 to 8 m. Instead Amsterdam Water chose to place the pipeline in the Pleistocene sand layer under the peat since the new freeway does not affect a pipeline at that depth. For the construction of a pipeline of this size (outside diameter of 1,200 mm), both concrete and steel can be used. The consortium chose steel for economic reasons.
During the preparation, it became apparent that the permit authority, Hoogheemraadschap Amstel Gooi en Vecht, would set exacting standards where the pipeline passed under the Geuzensloot. The Geuzensloot is an excavated canal at NAP level (Normal Amsterdam Water level). Because the banks of the canal are regarded as primary water-retaining structures, the Hoogheemraadschap standards are set for exceptional levels of construction stability and safety. For the crossings the new pipelines pass under the Geuzensloot in additional casing pipes with a diameter of 1,500 mm. This alteration to the plans meant more work and more time to get it done.
The entire project was carried out with minimal removal of groundwater. The removal of groundwater and its discharge are sensitive topics in the Netherlands — especially in view of the fact that the pipeline is being built at great depth through boring and a great deal of drainage would normally be required in peat soil to keep the pits dry. This meant that an alternative solution was required. The method chosen was more expensive than pumping out excess water, but did not have the discharge problem. The pits were designed to be waterproof and the pipe jacking was carried out without allowing water in flow. The pipes were jacked through a special rubber seal designed to withstand both the hydro-static pressure and the pipe movement to prevent ground water from entering the pit.
Amsterdam Water and the contractor’s consortium approached this project as a joint team from an early stage. The fruits are evident in the quality of the detailed plan, while short communication lines and quick responses for decisions saved time. The Visser & Smit Hanab/Dura Vermeer consortium was able to carry out the project in the most economical way and delivered the result that the customer wanted — an optimal win-win situation.
Where a technically complex project is concerned, a year passes by in no time, even if the twin pipeline to be built is only 5 km long. The pipeline was constructed entirely by micro-tunneling in Pleistocene sand at a depth of 10 m. Peat is located above this layer of sand, which is not the favorite kind of soil for pipeline owners or contractors. The performance of Visser & Smit Hanab/Dura Vermeer building consortium was unique in delivering this complex project on time, safely and to a very high quality.
Ton Timmermans is unit manager of trenchless technology at Dura Vermeer Ondergrondse Infra BV, Hoofddorp, Netherlands. Gerard Jonkergouw is manager of special projects at Visser & Smit Hanab BV, Papendrecht, Netherland.The article was first published in the Trenchless Technology International, May 2005.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …