Perforator® auger system aids motorway crossings project
Oct 06, 2010
Anyone driving around the UK at the moment using the motorway system will have noticed that there is a lot of work underway to install a huge automated traffic management system and information sign network. Part of this operation, organised by client The Highways Agency and its consulting engineer A.One+, one project has recently been underway on the M56 motorway between Junctions 9 and 16 under the ‘Triple Package Advanced Works’ designation.
The main contractor appointed to complete the project was A E Yates Ltd, with its sister company, A E Yates Trenchless Solutions Ltd, being awarded the trenchless installation works.
The majority of the crossings, some 25 out of 26, were completed using various HDD drilling rigs as per the project plan. The HDD bores varied in length between 40 and 100 m and comprised the installation of 4-way 110 mm diameter conduit pipes. However, at one particular crossing location near Helsby, the work site was very restricted in space, both on the launch and reception sides of the motorway, which meant that the use of the HDD technique was not possible, so another installation option had to be found.
Investigation of the options available led engineers at A E Yates to select the pilot auger microtunnelling technique for the limited-space site.
With the auger crossing site comprising ground conditions of very compact sand and weathered sandstone, the correct choice of installation technique was vital, whilst still being able to operate in the confined spaces on either side of the motorway.
Again careful consideration of the options available led to the choice of a Perforator PB85V pilot auger microtunnelling system as the best choice system for the situation in hand.
The auger crossing comprised the installation of a 45 m long, 300 mm diameter ‘lost steel tube’ which was to act as a carrier pipe for four 110 mm diameter purple PE80 MDPE conduit pipes, manufactured to DIN 8074/8075 specification and supplied by Drain Centre of Wigan, into which the fibre optic cables of the traffic management system would be installed.
However, for the M56 crossing project the contractor chose the PBA85V unit because the one very specific difference between the standard PBA85 rig and the PBA85V system is that, on the ‘V’ version, a gearbox normally used in the Perforator® PBA150 rig is fitted. This allows the ‘V’ unit to boast double the torque capacity of the basic unit. This would enable the bore to be completed efficiently in the harder ground conditions of the crossing site under the M56.
To complete the crossing first the rig is established in the start shaft on the line and level required for the crossing. As the pilot bore progresses the use of the Optic Electronic Navigation System (OEN), which is a laser based system, enables the pilot bore to be driven along the required route of the bore towards the target point.
With the bore at the correct size the pipe installation can then be completed by jacking the necessary pipe into place behind the auger chain whilst removing the displaced auger units at the reception shaft.
The PBA85V can also be utilised as an HDD rig where circumstances warrant and allow with a directional drilling system which can be fitted to the system which utilises the twin wall pilot rods of the standard PBA 85 system which are designed to accept high pressure HDD fluids, to create the initial bore. Subsequently, the high pressure drilling fluids are delivered to special rotary reamers using a purpose built pump, tank and mixer unit with a 2,000 litre capacity. Towing attachments and swivels have been specially designed to work within the PBA85V’s 65 tonnes of pullback capacity to enable the pull-in of the product pipe.
Installations on the M56 project as a whole, including the HDD works, started in January 2010 and were completed by March 2010. The HDD installations took an average of two restricted-hours night shifts each to complete. These were carried out in this manner because of traffic management constraints, restricted working space, and a requirement to dig the HDD rigs in at each site as each set-up was working adjacent to or under the live and open M56 motorway. Works on the auger crossing installation took 5 day shifts subsequent to shaft construction and site preparation.
According to Graham Smedley, managing director of Perforator® Ltd: "Using Perforator’s PBA guided boring systems on this auger crossing enabled the completion of what might otherwise have been a difficult installation to complete given the restrictions on the site in terms of both working close to an operational motorway and in the limited space available. We were very pleased to be able to provide a solution that proved so effective for the contractor. The PBA85V, and other members of the PBA family of pilot auger systems, enables the installation of pipes in straight-lines to grade in a wide variety of situations. Because of the system’s accuracy, installation of other utility pipe networks such as gas mains, water mains and drainage pipelines can also be achieved in areas surrounded by other services and known obstacles."
Commenting on the project for A E Yates site manager Sven Till said: "A difficult challenge was successfully undertaken by AEY Trenchless Solutions, in providing a solution to a problem for the Highways Agency by the use of the Perforator machine. A job well done"
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Perforator Limited
S13 9NP Sheffield
Phone:
+44 (0)1142 693258
Fax:
+44 (0)1142 889380