The project Captacion de Agua de Mar de San Pedro del Pinatar - a quatum jump in microtunnelling
Dec 14, 2006
This microtunneling project presents the internationally longest driven drilling length with DIN 2000 AVN in case of landoutfall. Particular challenges in this project were: length, geological conditions, time factor, and annulus lubrication.
The project on the Spanish shore included the construction of two pipelines to a seawater demineralisation plant. In the future 24 million cubic meters of sea water shall be supplied to the plant. The drilling project started in September 2005. The European Union supported the project by financing about 85 % of the construction sum. The total construction sum of the network amounted to 83 m €. The company DRAGADOS/FCC – SPAIN – was in charge of planning the ambitious project; the undertaking company was Sonntag Iberica. Dieter Bücher/Firma Dieter Bücherl Spezialtiefbau Amberg managed the construction from planning to finishing. Already in the planning phase the company BAROID IDP EUROPE had been entrusted with building a mud programme by which drivage in these dimensions would become feasible. Here, the main point was the annulus lubrication.
The automatic full-face cutter Herrenknecht AVN was used which had been modified for this particular application. The press capacity of the plant amounted to 1,200 tons. Here, an automatic annulus lubrication was very essential for this project. A separation plant equipped with mud screens and hydrocyclones provided by the company Schauenburg allowed a fast and clean preparation up to a cut point of 40,000 mm. The MAB performed 400 cubic meters per hour. The company Gollwitzer supplied the ferro-concrete drivage pipes (inside: DN 2000, outside: DN 2400). Intermediate jacking station provided by the company Gollwitzer were inserted along the drift.
According to the geological experts’ reports cross beddings of very different geology were expected in the subsoil: coral beds, sea salt licks, sand, loam, and silt. Especially at the end of the drift the occurrence of some possibly disturbing contaminants such as calcium salts and magnesium salts should be assumed due to the low lapping.
As a result of the inhomogeneous geological conditions and the contaminants to be expected it was necessary to develop an annulus lubrication that would resist all influences possible, especially the time factor. The fresh water for preparing the mixture of the lubrication suspension proved to be a first problem: the surface water which was taken from a little river was of insufficient quality when being used as the basis medium for an optimum annulus lubrication. The pH-value was 5.8; measurements of the German hardness revealed values of more than 25 degrees. Even the drinking water from the local network could not be used without pre-treatment.
Soda Ash + TUNNELGEL PLUS + NO SAG + PAC L + DINOMUL 2 kg Soda Ash were used to make the water user-friendly: the pH-value was increased to 8.5. After the treatment also hardness had optimum values. TUNNELGEL PLUS was the selected bentonite. It had already proven to be the best drilling bentonite in many problematic HDD drillings. NO SAG was used in order to essentially increase the gel strengths of the suspension. Furthermore, NO SAG stabilizes the suspension in the drilling in brackish water or salt water. PAC L should gain control over the contaminants to be expected. Furthermore, DINOMUL was added – a fluid additive that had been developed to reduce the rotation torques and stresses in the drill pipe. By the lubrication of a product pipe DINOMUL also reduces the traction in the HDD procedure. In addition, DINOMUL improves the stability of the borehole by forming a compact thin filter cake and protects reactive formation clays. The product DINOMUL also serves for increasing the lubrication effect in waterbasic muds and counteracting a sticking of the drill string. Experience has shown that DINOMUL can reduce the frictional forces by up to 60 %. In the present Microtunneling project the necessary thrusting forces were lower than 0.1 tons/m2 of the lateral surface. For the whole tunnelling about 1 cubic meter suspension per meter was needed for pumping. The maximum thrusting forces amounted to 600 tons, three of the 15 intermediate jacking stations were used for releasing the casing string only.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Ulrich Schröder
Sales & Service Europe
Phone:
+49 (0) 2761 838119
Fax:
+49 (0) 2761 839993